31.01.2024
In Vitry-sur-Seine (94), Eiffage Génie Civil is participating in the "Ardoines Ramp" project
The project, which is part of the municipality's modernisation plan, involves building a hydraulic compensation structure under the west ramp of the Ardoines crossing, and will also address the risk of flooding in the event of the Seine flooding.
Following a general pre-digging operation, the Foundations teams drilled the 175 anchor piles for the pool, ranging in diameter from 800 mm to 1200 mm, over a length of 17 m.
Once the roof slab covering almost 4,000 m² and its waterproofing had been completed, work continued on the underside with the mole excavation of 12,000 m³ of earth, the construction of a shotcrete perimeter wall and the invert of the structure.
By changing the phasing of the work, the overall schedule was shortened by almost a month, and 70% of the excavated material was reused as backfill.
The "top and down" method used - structure then mole earthworks - is helping to reduce the carbon footprint of this operation.
Completion is scheduled for June 2024!
-
04.07.2024Discover the behind-the-scenes video of the refurbishment...The Jeanne-Marvig tunnel boring machine arrived at the Toulouse Metro Line C construction site at the end of June. Discover the behind-the-scenes of its refurbishment...
-
01.07.2024In Toulouse, Eiffage Génie Civil inaugurates the Robert...Our teams participated in the inauguration of the Robert Poujade footbridge, formerly Rapas, on June 22, 2024, in the presence of Jean-Luc Moudenc, Mayor of Toulouse...
-
27.06.2024The Cutterhead of the Tunnel Boring Machine Jeanne...At the end of June, on the Toulouse Metro Line C construction site, the tunnel boring machine Jeanne Marvig was unveiled at the Colomiers Gare shaft site. The event...