GTE and Roland renovate runway 2 at Paris-Orly Airport
At the beginning of July, teams from the consortium set down their luggage at Orly for the renovation and upgrading of runway 2, following a phase of preparatory work completed in March, including the construction of a multi-tubular aircraft taxiway crossing.
Program:
- 35,000 m² of rigid pavement demolition ;
- 15,000 m² of concrete slab planing;
- Complete resurfacing of the 2,000 m x 60 m aeronautical runway with asphalt and adjacent connecting roads;
- Renovation of a 7,500 m² concrete taxiway;
- Installation of lighting systems;
- Construction of a crossroads in April-May 2024, the most demanding phase;
- 18 months of work.
Congratulations to the teams on this successful start!
Group: GTE, Roland, Eiffage Route Centre Ouest, Socalf and Cegelec.
Discover the project in video!
-
04.07.2024Discover the behind-the-scenes video of the refurbishment...The Jeanne-Marvig tunnel boring machine arrived at the Toulouse Metro Line C construction site at the end of June. Discover the behind-the-scenes of its refurbishment...
-
01.07.2024In Toulouse, Eiffage Génie Civil inaugurates the Robert...Our teams participated in the inauguration of the Robert Poujade footbridge, formerly Rapas, on June 22, 2024, in the presence of Jean-Luc Moudenc, Mayor of Toulouse...
-
27.06.2024The Cutterhead of the Tunnel Boring Machine Jeanne...At the end of June, on the Toulouse Metro Line C construction site, the tunnel boring machine Jeanne Marvig was unveiled at the Colomiers Gare shaft site. The event...