27.05.2024

ETMF has completed the onshore pull-in of the export cables for the future wind farm of Yeu and Noirmoutier islands.

A remarkable achievement following the landfall of the Eolmed and Provence Grand Large pilot farms in 2023, the Calvados offshore wind farm in 2022, and the Saint-Nazaire wind farm in 2020.

ETMF has completed the onshore pull-in of the export cables for the future wind farm of Yeu and Noirmoutier islands.

The offshore wind farm of Yeu and Noirmoutier islands will have a total capacity of 496 MW and will produce an average of 1,900 GWh annually, supplying nearly 800,000 people with sustainable electricity, which is more than the current population of Vendée. Its commissioning is planned for 2025.

Thank you to Prysmian and RTE – Réseau de Transport d'Électricité for their continued trust!