The steel structures for the bridges are shipped to Larvik from Eiffage Métal's welding yard in Lauterbourg. On site, the elements are assembled and then pushed onto temporary structures, sliding on Teflon pads and skids.
The next step is to weld the following steel sections to the rear edge before repeating the process. Around 135 meters are pushed at a time, at approximately two-month intervals.
This bridge marks the start of a series of projects, demonstrating our contribution to the development of Norwegian infrastructure with Nye Veier AS.
-
04.07.2024Discover the behind-the-scenes video of the refurbishment...The Jeanne-Marvig tunnel boring machine arrived at the Toulouse Metro Line C construction site at the end of June. Discover the behind-the-scenes of its refurbishment...
-
01.07.2024In Toulouse, Eiffage Génie Civil inaugurates the Robert...Our teams participated in the inauguration of the Robert Poujade footbridge, formerly Rapas, on June 22, 2024, in the presence of Jean-Luc Moudenc, Mayor of Toulouse...
-
27.06.2024The Cutterhead of the Tunnel Boring Machine Jeanne...At the end of June, on the Toulouse Metro Line C construction site, the tunnel boring machine Jeanne Marvig was unveiled at the Colomiers Gare shaft site. The event...